PPL Montana, LLC v. State, 229 P.3d 421 (2010), cert. granted, 131 S. Ct. 3019 (2011)

(plaintiff, wholesale generator of electricity, challenged award of summary judgment to defendant; trial court determined that defendant owned three riverbeds and was, thus, entitled to damages for plaintiff's use of riverbeds from 2000-2007 at hydroelectric power sites; on appeal, court affirmed on basis that rivers at issue were navigable when defendant became state in 1889 under navigability for title test).

CALT does not provide legal advice. Any information provided on this website is not intended to be a substitute for legal services from a competent professional. CALT's work is supported by fee-based seminars and generous private gifts. Any opinions, findings, conclusions or recommendations expressed in the material contained on this website do not necessarily reflect the views of Iowa State University.