Andrews v. Columbia Gas Transmission Corp., 544 F.3d 618 (6th Cir. 2008)

(defendant has right to clear an 80- foot swath of mature pine trees on plaintiffs' property in order to maintain natural gas pipeline pursuant to 1947 easement even though easement not utilized since 1947).

CALT does not provide legal advice. Any information provided on this website is not intended to be a substitute for legal services from a competent professional. CALT's work is supported by fee-based seminars and generous private gifts. Any opinions, findings, conclusions or recommendations expressed in the material contained on this website do not necessarily reflect the views of Iowa State University.